Small Capital Projects

Purchase 14 Portables for High Schools

This project includes purchase and installation of 14 portables, to accommodate high school student enrollment increases, including furniture and equipment, classroom technology, security systems, ramps, stairs, raised walkways, and utility connections.

  Location   HM Jackson HS – 1508 136th Street SE, Mill Creek, WA 98012
Cascade HS – 801 E. Casino Road, Everett, WA 98203
  Architect   Studio Meng Strazzara
  Contractor   Pacific Mobile & Electrical Contractor
  Estimated project cost   $2,800,000
  Estimated completion
  Fall 2020

Project update as of April 11, 2017
The site work for the portable pads is complete. The three portables are scheduled for delivery and install May 1-May 12.  They will be ready for occupancy for the 2017-2018 school year. 
 
 
 

Synthetic Turf Replacement at Everett HS Lincoln Field

This project includes replacement of the existing synthetic turf surface with new synthetic turf surface. The old surface is worn out due to wear and deterioration, and is in need of replacement. The original field was installed in 2004.

  Location   1898 25th St, Everett, WA 98201
  Architect   TBD
  Contractor   TBD
  Estimated project cost   $1,500,000
  Estimated completion
  Fall 2018
 
Project update as of February 9, 2017
Design of this project is scheduled to begin fall, 2017.
 
 

Preserve and Restore Exterior Finish at Everett HS Main Building

This project will include cleaning, sealing, caulking, and repointing of the existing exterior masonry and terra cotta, in order to preserve and enhance the historical façade of the building.

  Location   1898 25th St, Everett, WA 98201
  Architect   TBD
  Contractor   TBD
  Estimated project cost   $900,000
  Estimated completion
  fall 2019

Project update as of February 9, 2017
Design of this project is scheduled to begin fall, 2018.
 
 
 

Gateway MS Roof Replacement

The roofing project includes removal of the existing roofing on all buildings; and installation of new composition shingles, flashing, sheet metal and gutters on sloped-roof buildings; and installation of new PVC membrane roofing, flashing, sheet metal and gutters on flat-roofed buildings.

  Location   15404 Silver Firs Drive, Everett, WA 98208
  Architect   Rolluda Architects
  Contractor   TBD
  Estimated project cost   $2,000,000
  Estimated completion
  Fall 2017

Project update as of April 12, 2017
Kassel & Associates has been selected as the winning bidder and paperwork is underway to formalize that. All permits are either in hand or available for pickup. Construction is under budget and on schedule for work during the summer of 2017.
 
 
 

HVAC upgrades at 8 sites

The scope of work includes replacement of mechanical units and control systems, cooling tower replacement and boiler replacement at the following schools. Duct work replacement is not included.
  • Athletics building (unit and control system replacement)
  • Cascade High School (S Science Building (control system replacement in science building, boiler replacement)
  • Everett High School (unit and control system replacement in main building, boiler replacement in vocational building)
  • Gateway Middle School (cooling tower replacement, unit and control system replacement)
  • Madison Elementary School S Administration/Library (unit and control system replacement in administration building/library, boiler replacement)
  • Sequoia HS (cooling tower replacement)
  • Silver Lake ES Building ‘B’ (boiler replacement)
  • Whittier ES (boiler replacement)
 
  Location   Varies
  Architect   Rolluda Architects (Gateway MS only)
  Contractor   TBD
  Estimated project cost   $9,900,000
  Estimated completion
  summer 2023

Project update as of April 12, 2017
For the two Gateway items above, Kassel & Associates has been selected as the winning bidder and paperwork is underway to formalize that. All permits are either in hand or available for pickup. Construction is under budget and on schedule for work during the summer of 2017. The other HVAC projects will be phased through the summer of 2023.
 

HVAC technology infrastructures

Work includes upgrades to the district’s wireless infrastructure to support increased wireless connectivity, upgrades to the cooling systems in the rooms that house data equipment, and installation of electrical circuits that are powered by the backup generators.
 
  Location   Varies
  Architect   Hargis Engineering
  Contractor   TBD
  Estimated project cost   $2,300,000
  Estimated completion
  TBD

Project update as of April 13, 2017
Hargis Engineering, the selected engineering firm, submitted high school design drawings for staff review. This is a multi-year project. For summer of 2017, cabling and infrastructure upgrades will take place at all four high schools and wireless access points (WAPs) installation at two high schools (Everett HS & Sequoia HS).
 
 
 

Purchase property for future elementary school

Locate and purchase property suitable for a future elementary school.
  Location   Southeast portion of the district
  Real Estate Broker   New Ventures
  Consultants – Land Use   Brent Planning Solutions
  Consultants – Architect   Hutteball & Oremus
  Estimated project cost   $4,500,000
  Estimated completion
  January 2017

Project update as of April 13, 2017
The district has narrowed the property search to one primary location. Brent Planning Solutions and Hutteball & Oremus are working on a limited “fit” study for the site. The “fit” study is ongoing to look at the feasibility of this site. The fit study team visited the site on February 17 to conduct a walkover. The wetland biologist has provided a report and site plan showing the impact of wetlands and buffers. Using the new information, Hutteball & Oremus are working on an updated site plan.
 
 