Jefferson Elementary Modernization

  • This project provided a replacement or full modernization of the existing school, originally build in 1964. It included the extension of Cadet Way through to El Capitan Way. This project was funded by the $198,900,000 bond approved by the voters in 2006.

    New construction 42,000 s.f.
    Modernization 20,275 s.f.
    Total Area = 62,275 s.f.
  •   Location   2500 Cadet Way , Everett, WA 98208
      Architect   Hutteball and Oremus Architecture
      Project Began   Summer 2009
      Project Completed   Winter 2011