North MS updates

  • September 15, 2020

    Posted by Facilities & Planning on 9/15/2020

    Planning to submit to the board for final completion in October.  On September 1, the punch list walk for the one year warranty was completed.  The contractor is sending in the final billing and the remaining close out documents should follow soon.

    Comments (-1)
  • August 14, 2020

    Posted by Facilities & Planning on 8/14/2020

    An issue with outdoor occupancy sensors has been resolved and the final inspections have been completed.  Tying up loose ends with the remaining close out items and scheduling the one year warranty walk.

    Comments (-1)
  • June 15, 2020

    Posted by Facilities & Planning on 6/15/2020

    Tennis court nets have been installed the courts turned over to the school.  The track striping has been completed and the track has been turned over to the school.  Work is progressing on project close out. Billings have been reviewed and are setup for final change order.  

    Comments (-1)
  • May 15, 2020

    Posted by Facilities & Planning on 5/15/2020

    Tennis court nets will be installed next week at the end of the curing period.  The track rubberized surface is complete and striping is scheduled for today, weather permitting.  Some commissioning work and project close out remains.

    Comments (-1)
  • April 27, 2020

    Posted by Facilities & Planning on 4/27/2020

    The tennis court resurfacing has been completed and it is locked during the curing period.  Nets will be installed and locks removed in the third week of May.  The contractor installing the rubberized track surface has mobilized as scheduled so materials and equipment are now on site, although weather has prevented them from starting work.  Some commissioning work and project close-out remains.

    Comments (-1)
  • April 15, 2020

    Posted by Communications on 4/15/2020

    The last of the commissioning work is being scheduled.  Repair of cracks in the tennis courts is underway, to be followed by resurfacing.  The rubberized track surfacing has been rescheduled to start 4/20 due to extra coordination required at this time.  Work is underway on project close-out items.

    Comments (-1)
  • April 1, 2020

    Posted by Communications on 4/1/2020

    Some additional follow up delayed the final Test & Balance work, which has now been completed.  The final report is due at the end of this week, to enable commissioning to continue.  The rubberized surface for the track and the refinishing of the tennis court are both scheduled to start 4/6/2020.

    Comments (-1)
  • March 16, 2020

    Posted by Communications on 3/16/2020

    The final Test & Balance report is due at the end of this week, enabling commissioning to continue.  The tennis court resurfacing and track rubberized surface are both scheduled to start April 1.

    Comments (-1)
  • February 28, 2020

    Posted by Communications on 2/28/2020

    The new softball field has been turned over to the school.  The resurfacing of the tennis courts and the rubberized top layer for the track are both scheduled for April, pending appropriate weather.

    Comments (-1)
  • February 14, 2020

    Posted by Communications on 2/14/2020

    The synthetic turf needs one more day and it will be complete and then the softball field and track will be turned over to the school.  Six trees need to be sourced and planted for landscape to be complete.  The punchlist is ready to backcheck.  Commissioning is 75% complete.  The resurfacing of the tennis courts and the rubberized top layer for the track are both scheduled for April, pending appropriate weather.

    Comments (-1)