North MS updates

  • November 14, 2019

    Posted by Facilities & Planning on 11/14/2019

    The process of moving into the renovated band and choir rooms is underway. When complete, the Aux Gym will be converted back for use by the P.E. department. Work has progressed well on the new parking lot. Detention pipe placement and crushed rock cover has been completed and curbs are being poured today. All of the cut on the field has been removed, in addition to some soft soils, and rock has been placed over most of it. Pipes for the backstop at the softball field have been installed.

    Comments (-1)
  • October 15, 2019

    Posted by Communications on 10/15/2019

    The new weight room has been turned over to the school.  Finishes have begun in the band and choir rooms.  Earthwork for the new parking lot and softball/track side of the field continue as weather allows with crushed rock fill being placed on the detention pipes under the parking lot and subgrade drainage under the softball/track is about ½ complete.

    Comments (-1)
  • October 1, 2019

    Posted by Communications on 10/1/2019

    Work continues on the music area modernization and the new weight room is nearly complete.  Unusually wet weather has slowed the earthwork for the new parking lot and the softball/track side of the new field.

    Comments (-1)
  • September 16, 2019

    Posted by Communications on 9/16/2019

    School started on 9/4/19, as scheduled, with students occupying the new building.  The architect’s punch list has been generated for the new building and delivered to the contractor.  With the Band and Choir rooms under renovation, Band has been temporarily setup in the Aux Gym and Choir in the Health room.  Work continues on the new parking lot and has been recently suspended on the West side of the field due to the recent heavy rains.  The East side of the field is the football field and is complete and in use by the school.

    Comments (-1)
  • September 3, 2019

    Posted by Communications on 9/3/2019

    The synthetic turf football field is nearly complete. Final sign-off for occupancy of new building has been approved. Work done over the summer on the gymnasium building is nearing completion. The band and choir rooms are under construction and will be ready for occupancy in October. Staff is now in the new building preparing for students.

    Comments (-1)
  • August 1, 2019

    Posted by Communications on 8/1/2019

    The elevator, fire alarm system, fire sprinkler system and kitchen have been signed off by the associated inspector. All utilities are installed and operational. Paving of the parking lots is complete. Paving if the north access road that connects to 174th street will be complete before the start of school. Landscaping is underway. The under field drainage is complete at the play field and the contractor has begun placing topsoil on the play field. The play structure will be complete by the end of August. Classrooms are complete with the exception of punch list. The office staff has moved into the building with teachers to move in on August 19. Furniture has been delivered and distributed throughout the school.

    Comments (-1)
  • July 30, 2019

    Posted by Communications dept. on 7/30/2019

    North Middle School facitilies update Check out the interior of North Middle School! Crew is working hard to get it finished and ready to welcome new students on the first day of school.

    Comments (-1)
  • July 19, 2019

    Posted by Communications dept. on 7/19/2019

    North Middle School project update

    Roofing continues on the main gym and music/choir areas, and exterior finishes on the new building are 98% complete.

     

    Inside the new building, ceilings continue with lights and HVAC diffusers installation. All permanent utilities are in place and the new building remains on track for housing students at the start of school in the fall.

    Comments (-1)
  • May 31, 2019

    Posted by Communications on 5/31/2019

    Site work for the new synthetic field began Tuesday on the East 1/3 of the field, while the school continues to use the other 2/3.  Brick is complete and exterior siding is about 75%.  Interior finishes continue and lights are being placed into the ceiling grid.  Cabinets have been delivered and are being installed.  Grinding of the floors for the science and art rooms is well underway.  Planning continues in preparation for construction throughout the campus during the summer.

    Comments (-1)
  • May 21, 2019

    Posted by Communications dept. on 5/21/2019

    Two buildings with siding being installed Brick siding is complete and the remaining exterior siding is about 60% complete.

     

    All utility providers have made final connections to the new building. Paint, ceiling grid, and ceramic tile finishes are underway and cabinets are being installed.

     

    The elevator cab and hoist are in place. The kitchen exhaust hood and walk-in cooler and freezer have been installed.

     

    The contractor is preparing for a busy summer with plans to work throughout the entire school site when school is out.

    Comments (-1)