North MS updates

  • April 15, 2020

    Posted by Communications on 4/15/2020

    The last of the commissioning work is being scheduled.  Repair of cracks in the tennis courts is underway, to be followed by resurfacing.  The rubberized track surfacing has been rescheduled to start 4/20 due to extra coordination required at this time.  Work is underway on project close-out items.

    Comments (-1)
  • April 1, 2020

    Posted by Communications on 4/1/2020

    Some additional follow up delayed the final Test & Balance work, which has now been completed.  The final report is due at the end of this week, to enable commissioning to continue.  The rubberized surface for the track and the refinishing of the tennis court are both scheduled to start 4/6/2020.

    Comments (-1)
  • March 16, 2020

    Posted by Communications on 3/16/2020

    The final Test & Balance report is due at the end of this week, enabling commissioning to continue.  The tennis court resurfacing and track rubberized surface are both scheduled to start April 1.

    Comments (-1)
  • February 28, 2020

    Posted by Communications on 2/28/2020

    The new softball field has been turned over to the school.  The resurfacing of the tennis courts and the rubberized top layer for the track are both scheduled for April, pending appropriate weather.

    Comments (-1)
  • February 14, 2020

    Posted by Communications on 2/14/2020

    The synthetic turf needs one more day and it will be complete and then the softball field and track will be turned over to the school.  Six trees need to be sourced and planted for landscape to be complete.  The punchlist is ready to backcheck.  Commissioning is 75% complete.  The resurfacing of the tennis courts and the rubberized top layer for the track are both scheduled for April, pending appropriate weather.

    Comments (-1)
  • February 3, 2020

    Posted by Communications on 2/3/2020

    Fence work to close up tennis courts has been completed, as well as the softball backstop fencing.  The synthetic turf seams are completed and crews await dry weather for the infill.  The parking lot landscaping is nearly complete.

    Comments (-1)
  • January 15, 2020

    Posted by Communications on 1/15/2020

    North Middle School Parking Lot The new parking lot is now in use.  The synthetic turf has been laid across the softball field with seaming and turf marking strips being fastened in place.  Commissioning is about 75% complete.

    Comments (-1)
  • January 2, 2020

    Posted by Communications on 1/2/2020

    The new parking lot will be turned over to the school on 1/6/2020 and the synthetic turf for the softball field will begin on that same date.  The pervious paving for the track is complete.  Commissioning is underway.

     

    Comments (-1)
  • December 16, 2019

    Posted by Communications on 12/16/2019

    The new parking lot has been paved.  Striping, signage, landscaping and a few other details are underway to complete the work, which depending on weather conditions, may be ready for use after the holiday break.  Resurfacing of the tennis courts, currently in service as the temporary parking lot, will occur in the Spring, contingent on warmer weather.  The pervious paving for the track base is currently underway and the synthetic turf installation will take place in January.  The rubberized track top surface will be placed in May or June when suitable weather is on hand, and will complete the North Middle School Modernization project.

    Comments (-1)
  • December 2, 2019

    Posted by Facilities & Planning on 12/2/2019

    Curbs and sidewalks are 90% complete in the new parking lot and the base course of aggregate is in place. Fine grading is underway in preparation for paving. The electrician has set the parking lot light poles and will be wiring them this week. The base course of aggregate is in place on the field and fine grading will begin this week. The current expectation is that this work will be complete this month, except for the track surface, which will be placed in the spring due to weather. The tennis courts, currently in use as the temporary parking lot for the school, will have nets replaced by the end of this month, but resurfacing will have to wait for late spring when temperatures are suitable for that work.

    Comments (-1)