North MS updates

  • September 3, 2019

    Posted by Communications on 9/3/2019

    The synthetic turf football field is nearly complete. Final sign-off for occupancy of new building has been approved. Work done over the summer on the gymnasium building is nearing completion. The band and choir rooms are under construction and will be ready for occupancy in October. Staff is now in the new building preparing for students.

    Comments (-1)
  • August 1, 2019

    Posted by Communications on 8/1/2019

    The elevator, fire alarm system, fire sprinkler system and kitchen have been signed off by the associated inspector. All utilities are installed and operational. Paving of the parking lots is complete. Paving if the north access road that connects to 174th street will be complete before the start of school. Landscaping is underway. The under field drainage is complete at the play field and the contractor has begun placing topsoil on the play field. The play structure will be complete by the end of August. Classrooms are complete with the exception of punch list. The office staff has moved into the building with teachers to move in on August 19. Furniture has been delivered and distributed throughout the school.

    Comments (-1)
  • July 30, 2019

    Posted by Communications dept. on 7/30/2019

    North Middle School facitilies update Check out the interior of North Middle School! Crew is working hard to get it finished and ready to welcome new students on the first day of school.

    Comments (-1)
  • July 19, 2019

    Posted by Communications dept. on 7/19/2019

    North Middle School project update

    Roofing continues on the main gym and music/choir areas, and exterior finishes on the new building are 98% complete.

     

    Inside the new building, ceilings continue with lights and HVAC diffusers installation. All permanent utilities are in place and the new building remains on track for housing students at the start of school in the fall.

    Comments (-1)
  • May 31, 2019

    Posted by Communications on 5/31/2019

    Site work for the new synthetic field began Tuesday on the East 1/3 of the field, while the school continues to use the other 2/3.  Brick is complete and exterior siding is about 75%.  Interior finishes continue and lights are being placed into the ceiling grid.  Cabinets have been delivered and are being installed.  Grinding of the floors for the science and art rooms is well underway.  Planning continues in preparation for construction throughout the campus during the summer.

    Comments (-1)
  • May 21, 2019

    Posted by Communications dept. on 5/21/2019

    Two buildings with siding being installed Brick siding is complete and the remaining exterior siding is about 60% complete.

     

    All utility providers have made final connections to the new building. Paint, ceiling grid, and ceramic tile finishes are underway and cabinets are being installed.

     

    The elevator cab and hoist are in place. The kitchen exhaust hood and walk-in cooler and freezer have been installed.

     

    The contractor is preparing for a busy summer with plans to work throughout the entire school site when school is out.

    Comments (-1)
  • May 15, 2019

    Posted by Communications dept. on 5/15/2019

    Brick is complete and exterior siding is about 60%.  All utilities are connected.  Paint, ceiling grid and ceramic tile finishes are underway and cabinets are being installed.  The elevator cab and hoist are in place.  The kitchen exhaust hood and walk-in cooler and freezer have been installed.  We are preparing for a busy summer with plans to work throughout the entire school site when school is out.

    Comments (-1)
  • May 7, 2019

    Posted by Communications dept. on 5/7/2019

    North Middle School construction site The North Middle School project continues on schedule.

     

    The electrical rough-in is now complete and installation of sheetrock, mudding and taping continues. Installation of the ceiling grid has begun and the exterior brick veneer is nearly complete with metal and cementitious siding well underway. Frontier has installed the cable for the new phone service and sitework around the building has begun, including setting of the new lighting pole bases.

    Comments (-1)
  • April 15, 2019

    Posted by Communications on 4/15/2019

    Interior painting has begun.  Elevator installation began 4/10/19 and will continue for about three weeks.  Electrical and mechanical rough-ins are nearing completion, as is window installation.  Sheetrock installation and taping continue.  Wood siding and data cabling started today.  Brick and metal siding are complete in the courtyard and continue in other areas.  The West connector has been left open to allow access to the courtyard.  Work to close this up begins next Monday.

    Comments (-1)
  • April 9, 2019

    Posted by Communications dept. on 4/9/2019

    Siding going up, crane lifting siding The exterior siding has begun, brick continues to be installed and windows are 75% installed. Sheetrock mudding has begun and painting will soon follow.

     

    Most mechanical units have been placed and the elevator parts have begun to arrive. Permanent power and the gas service are on. The new boy’s locker room was turned over for school use on April 8.

    Comments (-1)