Woodside ES project updates

  • May 31, 2019

    Posted by Communications dept. on 5/31/2019

    The OSPI D-7 form was submitted and the D-8 subsequently issued, authorizing the opening of bids for the project.  Four bids were received 5/30/19 with an apparent low bidder that is close to the project budget.  Due diligence is underway for this apparent low bidder and if it is positive, the board will be asked to award the bid during their regular meeting on 6/18/19.  Construction is anticipated to begin in July, as scheduled.

    Comments (-1)
  • May 15, 2019

    Posted by Communications on 5/15/2019

    Two pre-bid walk-through meetings were conducted and a total of 10 general contractors attended.  This qualifies these ten to submit a bid for the project, due on 5/30/19.  One addendum has been issued to date.  The D-7 is in final review prior to be submitted.

    Comments (-1)
  • May 1, 2019

    Posted by Communications on 5/1/2019

    The first advertisement for bids ran in today’s papers with a due date of 5/30/19.  The D-6 has been received from OSPI and the D-7 is nearly ready to submit.  The original Conditional Use Permit requires a Minor Revision for this project and the county has requested some changes to our submittal, which are in progress.

    Comments (-1)
  • April 15, 2019

    Posted by Communications on 4/15/2019

    OSPI has signaled that the D-6 answer to the D-5 submittal is about to go out. Constructability Review comments have been reviewed and incorporated into the design as applicable. Construction documents at about 95% completion were received today and will be reviewed in preparation for going out to bid on 5/1/19. An option to relocate the school to the former Alderwood MS site has been reviewed and rejected, the modernization will continue as an occupied modernization project with four phases.

    Comments (-1)
  • April 9, 2019

    Posted by Communications dept. on 4/9/2019

    Conceptual drawing of Woodside Elementary library

    A milestone was recently reached as the Mitigated Determination of Non Significance was issued (MDNS) completing the State Environmental Policy Act (SEPA) review for the project.

     

    The Conditional Use Permit has been submitted to the county. Plans have been submitted for the building permits and the state electrical review. The Constructability Report is being reviewed by the design team. Bid documents are 95% complete with plans to bid on May 1.

    Comments (-1)
  • Mar. 1, 2019

    Posted by Communications on 3/1/2019

    The MDNS is in the two week comment stage.  The drawings have been submitted for permit review.  The Constructability Review is underway and will complete within the next two weeks. The project is scheduled to bid in May.

    Comments (-1)
  • Feb. 15, 2019

    Posted by Communications on 2/15/2019

    The submittal is in for CUP revision, which incorporates the SEPA checklist.  Work is progressing well for the OSPI D-form documents.  The project phasing has been dialed in and the Construction Documents are at nearly 90%.  The Constructability Review kick-off is scheduled for Thursday, 2/21/19.  The architect plans to submit for the building permit next week.

    Comments (-1)
  • Feb. 1, 2019

    Posted by Communications on 2/1/2019

    The OSPI D-5 form is nearly ready to submit.  The permit set of CD documents was delivered as scheduled last week.  Internal review of the SEPA/CUP materials is underway in preparation of submittal to the county.  The class room moves portion of project phasing details are complete and the design team will finalize their details.  The Constructability Review is scheduled for the third week of February.

    Comments (-1)
  • Jan. 24, 2019

    Posted by Communications dept. on 1/24/2019

    Architects rendering of library with high ceiling and lots of natural light At the December 2018 Open House, Studio Meng Strazzara Architects shared some renderings of the project. This rendering is the new library which will be located the two-story administration and library building. 

     

    Construction will begin this summer, with the completion of the project in the spring of 2021.

    Comments (-1)
  • Dec. 31, 2018

    Posted by Communications on 12/31/2018

    Owner edits for Design Development are due to the architect in January and they will start 90% drawings.

    Comments (-1)