Woodside ES project updates

  • March 11, 2021

    Posted by Facilities and Planning Department on 3/25/2021

    All buildings have been turned over for school district use and are occupied.  Work continues to restore the former construction area on the field and finish the final landscaping work.  A feature wall is to be installed on the stair by the library later this month and the tackable wall covering is due to ship this week with about two weeks of install work that is expected to be complete by the first week of April.  Commissioning and close out are underway and the project is on track to wrap up in April as originally scheduled.

    Comments (-1)
  • February 16, 2021

    Posted by Facilities & Planning on 2/16/2021

    The bus lane has been paved.  The café/gym building D and building C have both been turned over to ESD.  Furniture is scheduled for installation in building D on 2/22/2021.  The construction area on the field is being restored.  Punch list work continues throughout the project.

    Comments (-1)
  • January 20, 2021

    Posted by Facilities & Planning on 1/21/2021

    The bus lane asphalt grind/overlay is underway.  The café/Gym, building D is in the process of turnover/move-in.  Construction continues in classroom building C where ceiling grid is in place and floor prep for new flooring has just begun and trades are busy with trim-out work.  The courtyard is complete, and landscaping continues.  The contractor is downsizing their lay-down and work areas.  The first group of students successfully returned to on-site instruction 1/18/2021 when Developmental Kindergarten resumed in building A.

    Comments (-1)
  • November 30, 2020

    Posted by Facilities & Planning on 11/30/2020

    In the Café/Gym, building D, the final flooring is being installed and the finishing touches are being completed. The data systems are expected to be functional this week.  Furniture was delivered and setup last week.  In building C, most of the framing is complete and sheetrock has begun on one side of walls while wall rough-in for plumbing and electrical continue.  Mechanical units were set last week and the sidewalks around the building will be completed as soon as the groundwater remediation work has been installed on the East end of the building.  Plants arrived last week and have been planted, except for the active construction areas around buildings C and D.

    Comments (-1)
  • November 1, 2020

    Posted by Facilities & Planning on 11/20/2020

    The gym in building D has electrical finishing details underway.  Paint and ceilings are nearly complete on the cafeteria side of the building.  Plumbing fixtures are set in the restrooms and partitions are up.  Perimeter framing on building C is in place and roofing is ready to start.  Below that, selective demolition is nearly complete with mechanical and electrical rough-in work underway.  Sidewalks in the courtyard are about 60% complete with the remaining being around building C and that work will be undertaken when vehicle traffic to building C has been completed.  Painting of the covered play is complete, and the wood play chips are in place on the new playground.  Site restoration south of buildings A and B is nearly complete with only planting remaining.

    Comments (-1)
  • October 20, 2020

    Posted by Facilities and Planning on 10/21/2020

    The gym in building D has been painted.  Acoustic panels, wall cladding, pads and basketball hoops are installed.  Finishing touches are ongoing.  The cafeteria side of building D has ceilings going in and painting is underway.  The kitchen hood and walk-in cooler and freezer are in place.  Ceramic tile in the bathrooms in in place with flooring going in.  The projectors in buildings A, B and G have all been commissioned and are ready for use.  Roofing materials are expected this week for building C.  Abatement activities are complete and the selective demolition is fully underway.  Sidewalks are about 40% complete in the courtyard area with focus on completing those adjacent to and on the pathway to occupied buildings.  Painting of the covered play underside is nearly complete with the exterior to follow.  The playground equipment is 90% set with wood chips to follow.

    Comments (-1)
  • September 15, 2020

    Posted by Facilities and Planning on 10/1/2020

    School has begun with some teachers conducting distance learning from their class rooms while others do so from home.  The site is split with the main parking lot, new office/library and class room building A and B occupied for school and the café/gym building, class room building C, covered playshed, bus lane and courtyard are cordoned off for construction.  Punch list work continues in the office/library and B.  The roof on building D has been completed and sheetrock is hung in the gym.  All slabs have been poured and rough-in work is nearing completion.  Air handling units are expected to arrive and be set next week.  In building C, the perimeter of the ceiling is being opened up to facilitate structural work and the roofing will begin next week.  Foundations are being dug in the courtyard for the planter areas.

    Comments (-1)
  • August 14, 2020

    Posted by Facilities and Planning on 9/1/2020

    Furniture is being installed in the new office/library building with contents scheduled to be moved in next week.  Building B has flooring going down and furniture is scheduled to arrive 8/17 with contents to follow late next week.  The concrete slab and foundations for the former office/library building have been removed and the courtyard grading is underway.  In building D, the slab has been poured in the kitchen area and shingle roofing is being installed.  The concrete flatwork around the new office/library is underway along with preparations for grinding and overlaying the parking lot.

    Comments (-1)
  • July 15, 2020

    Posted by Facilities and Planning on 7/31/2020

    In building B, the topping slab has been poured and painters are painting walls, ceiling grid is going up and finish work has begun for mechanical and electrical devices.  Also, roof insulation is being placed with shingles to follow.  In building D, spray foam insulation has been completed in the band and cafeteria area and continues in the custodial and kitchen areas, structural upgrades are nearly complete and underground plumbing is nearly complete.  Preparations for the first of two concrete pours have begun.  Underground utility work continues along the south sides of buildings D and C.  For building F, the covered playshed, an overlay of roof sheathing is needed and has been approved and that will commence soon with new roofing to follow.  In building G, light fixtures and other ceiling mounted devices are well underway, casework has been placed and flooring is about to begin.  Work to refeed the portables from the new power and data sources is progressing well and should be complete in a couple weeks.  The contractor has begun planning for the work in the parking lot that will take place this summer.

     

    Comments (-1)
  • June 15, 2020

    Posted by Facilities and Planning on 6/30/2020

    Framing in building B is nearly complete as is spray foam in the walls.  Evaluating sub-floor prior to placement of topping slab.  Carpentry crews are working on structural upgrades in building D.  In building G, ceiling grid is well underway and most casework is set.  Underground utilities continue along the bus loop, coordinated for allowing access to the school as needed.

     

    Comments (-1)