Woodside ES project updates

  • April 15, 2020

    Posted by Communications on 4/15/2020

    The carpet has been installed in building A and the building is substantially complete.  In building G, sheetrock installation is taking place on the upper floor and finishing on the lower level.  The last of the windows are being installed this week.  Building B has been emptied of furniture and school contents and selective demolition is underway beginning its modernization process.  The cafeteria/gym building is being packed with movers scheduled at the end of this week to remove school contents and furniture, thereby allowing an early start since school is out until the fall.

    Comments (-1)
  • April 1, 2020

    Posted by Communications on 4/1/2020

    Finishes are nearly complete in building A and furniture arrived today.  In building G, the boilers have been started, the fire alarm is online and HVAC is undergoing functional testing.  Windows are 60% installed. Work is underway to tie the existing low voltage systems to the new ones in order to re-establish campus wide connectivity for intercom, intranet, phones, security, etc.

    Comments (-1)
  • March 16, 2020

    Posted by Communications on 3/16/2020

    In building A, the ceiling grid is nearly complete with lights and HVAC diffusers and grilles following.  Cabinetry and door hardware started last week and painting is well underway.  Roofing is substantially complete.  Flooring is scheduled to start today.  In the new office/library building, mechanical and electrical rough-in work is nearing completion and roofing is well underway.  Sheetrock installation has begun.  The new electrical service has been energized.

    Comments (-1)
  • February 28, 2020

    Posted by Communications on 2/28/2020

    In building A, painting and ceiling grid are underway.  Roof insulation and nail-base boards are being installed.  In the new office/library building interior wall framing is complete with mechanical and electrical rough-ins nearly complete on the ground floor and well underway on the upper level.  Perimeter framing is in and roof insulation will soon follow.

    Comments (-1)
  • February 14, 2020

    Posted by Communications on 2/14/2020

    The roof on the new building is dried-in.  Mechanical and electrical rough-in work continues below.  For Building A, the sub-floor was poured and looks great.  The existing roofing has been torn off and it is dried-in, including the A/B connector.  Windows are in and interior finishes are beginning.

    Comments (-1)
  • February 3, 2020

    Posted by Communications on 2/3/2020

    Metal roof decking is in place on the new building, to be followed by roofing as weather allows.  The roof tie-ins for the A/B connector are underway.  The sub-floor in building A is going in this week.

    Comments (-1)
  • January 15, 2020

    Posted by Communications on 1/15/2020

    All floor slabs in the new building are in place and wall framing is just beginning as are rough-ins for mechanical and electrical.  In Building A, most of the sheetrock is up and taping is underway.  Painting is expected to take place at the end of the month, followed by pouring back the subfloor.  The A/B connector has walls framed with ceiling framing to begin next.

    Comments (-1)
  • January 2, 2020

    Posted by Communications on 1/2/2020

    Most of the structural steel for the new building is standing.  The erectors are working on finishing details.  The second floor slab in the new building is scheduled to be poured tomorrow, if weather cooperates.  The contractor is setting up temporary heat in Building A to enable work with finishes to continue.

    Comments (-1)
  • December 16, 2019

    Posted by Communications on 12/16/2019

    About half of the structural steel has been erected for the new building.  The floor slab connecting building A and B has been poured and framing has begun.  Drywall is underway in Building A. Preparations are wrapping up for receiving the mechanical units in both buildings.  Due to several unforeseen conditions, the schedule for occupying Building A has been moved to Spring break and occupancy of Building G (office/library) has been moved to Summer.  The overall scheduled end date for the project has not changed at this time.

    Comments (-1)
  • December 2, 2019

    Posted by Facilities & Planning on 12/2/2019

    Concrete work at the utility yard on the East side of building A is underway. The setting of structural steel for the new building begins this week. Underground rough-in is underway for the new connector between buildings A and B. Framing in building A is 95% complete. Mechanical and electrical rough-ins are nearly complete as well.

    Comments (-1)