Jackson Elementary School Replacement

This photo was taken at the construction site of Jackson Elementary in July of 2026.

Estimated project cost: $54,440,000
Estimated start date: Summer 2025
Estimated Phase I completion: Fall 2026
Estimated Phase II completion: Spring/Summer 2027
Description
This project includes demolition of the existing school building. New construction will be steel with masonry and metal exterior cladding with a membrane roof. The existing covered play structure will be modernized. Site amenities include parking for approximately 100, a parent drop-off/pick-up loop, bus loop and parking for buses, new playground area and grass playfield restoration. The capacity of this school will be increased by adding new permanent classrooms. The school will be fully occupied during construction.