North Middle School updates

  • Dec. 27, 2018

    Posted by Communications on 12/27/2018

    Roofing started on 12/17/18. Metal stud placement continues, as well as interior rough-ins and slab-on-deck for the 2nd floor.

    Comments (-1)
  • Dec. 7, 2018

    Posted by Communications on 12/7/2018

    Structural steel was all in place as of 12/5/18.  All concrete slab-on-grade was poured as of 12/6/18.  Metal stud placement continues, as well as interior rough-ins.

    Comments (-1)
  • Dec. 5, 2018

    Posted by Communications dept. on 12/5/2018

    Drone view of school with crane placing steel Approximately 80% of the first floor and 45% of the second floor concrete slab has been poured. Structural steel erection is 95% complete and the contractor anticipates “topping out” the structural steel in the next week.

     

    Exterior and interior metal stud framing is underway. Mechanical, electrical and plumbing rough-in continues.

    Comments (-1)
  • Nov. 19, 2018

    Posted by Communications dept. on 11/19/2018

    Structural steel erected Approximately 60% of the first floor and 25% of the second floor concrete slab has been poured. Structural steel erection and interior and exterior framing continue.

     

    Rough-in for mechanical, electrical and plumbing in the structure has begun. The new underground conduits for the main electrical feed to the school are being completed this week.

    Comments (-1)
  • Oct. 26, 2018

    Posted by Communications dept. on 10/26/2018

    Ariel view of steel beams and first floor concrete poured. The large area of the first floor has been poured. The contractor continues to excavate, form and pour concrete foundations. The structural steel is being delivered to the site now and continues through the end of the month and the contractor has begun erecting structural steel.

     

    Click to watch crane moving steel beams!

    Comments (-1)
  • Oct. 12, 2018

    Posted by Communications dept. on 10/12/2018

    Ariel view of North Middle School construction site.   Check out this bird's-eye view of the construction going on at North Middle School!

     

    The building contractor has framed new electrical main data room and boiler room and continues to form/pour concrete foundations. Workers are fine-grading and preparing to pour concrete slab at first floor this week.

    Comments (-1)
  • Sept. 12, 2018

    Posted by Communications on 9/12/2018

    School began on time in the interim layout that will be in place for the 2018-19 school year.  Building foundations for the new building are about 25 percent complete and that work continues. 26th Street has been closed from Rainier Avenue West to the edge of the temporary parking lot. This allows students to cross the street without any vehicular traffic and also joins the construction area with the construction staging area. 

    Comments (-1)
  • Aug. 30, 2018

    Posted by Communications dept. on 8/30/2018

    Demolition has finished, some buildings are gone The North Middle School modernization is coming along! This summer abatement and demolition of the main building was completed. Underground utilities and concrete foundations are currently being installed.

    Comments (-1)
  • Aug. 15, 2018

    Posted by Communications on 8/15/2018

    Building 100 has been removed in its entirety and a gravel pad is being prepared for the new building.  Movers return next week to move the boxes and furniture out of the gym and into the portables.  Many finishing details are underway to prepare this interim layout for the upcoming school year.

    Comments (-1)
  • Aug. 3, 2018

    Posted by Communications on 8/3/2018

    Building 100 has been demolished with only the concrete floor slab remaining along with a portion of the debris from the building.  The build-out of the former library space into class rooms and offices has nearly been completed.  Focus is on finishing details and one more move that are needed for the start of school.

    Comments (-1)