Tambark Creek ES project updates

  • June 12, 2019

    Posted by Communications dept. on 6/12/2019

    The interior and exterior finishes are in process.  The contractor is installing the brown metal siding.  The concrete curbing and asphalt base for the road and parking areas are in process.  Utilities will be operational by mid-June.  Phone and fiber connections from the vendor are complete.   Elevator was delivered and is expected to be operational by 6/18.  90% of kitchen equipment and break-out store windows are installed.  The courtyard glass curtain wall is complete.

    Comments (-1)
  • June 4, 2019

    Posted by Communications dept. on 6/4/2019

    Drone photo of Tambark Creek as of June 2019

    Tambark Creek Elementary is on schedule for opening in fall of 2019. Interior and exterior finishes are in process and the contractor started installation of the brown metal siding in the courtyard. The concrete curbing and asphalt base for the road and parking areas are in process. Utilities will be operational by mid-June. The outline of the play toy area and the playground (with drainage) can be seen from this aerial photo.

    Comments (-1)
  • May 21, 2019

    Posted by Communications Dept. on 5/21/2019

    Casework being installed Installation of the large exterior store front windows began last week. Exterior windows and siding installation continues. The new boilers, pumps, and associated piping have been installed.

     

    The main electrical switch gear is nearing completion, with PUD scheduled to bring power to the building by the end of the month.

     

    Finish work is underway throughout the classroom wing, including casework, ceiling tile, wall coverings, white boards, painting, and interior glazing.

    Comments (-1)
  • May 7, 2019

    Posted by Communications dept. on 5/7/2019

    Tambark Creek Elementary School construciton site At Tambark Creek Elementary School exterior windows are being installed and roofing, interior sheetrock and lockers are complete.

     

    Tackable wall panels, white boards, and casework are being installed in the classroom wings. Floor polishing and ceramic tile will be complete this month. Plumbing, electrical and mechanical rough-in are about 95% complete. Parking-lot grading, exterior lighting, and curbing are in process.

    Comments (-1)
  • April 30, 2019

    Posted by Communications dept. on 4/30/2019

    Exterior windows are being installed. Roofing, interior sheetrock and lockers are complete. Tackable wall panels, white boards, casework are being installed in the classroom wings.  Floor polishing and ceramic tile will complete by mid-May.  Plumbing, electrical and mechanical rough are about 95% complete. Parking-lot grading, exterior lighting, and curbing are in process. Sidewalk sample will be reviewed 1st week of May before pouring.  Elevator install is planned for May 10.

    Comments (-1)
  • April 10, 2019

    Posted by Communications on 4/10/2019

    Roofing is approximately 98% complete. Exterior siding and windows are being installed. Interior sheetrock is approximately 75% complete. Paint and tackable wall panels are being installed in the classroom wings along with casework.  Floor polishing of the restrooms will be complete by 4/15 and tiling will complete the next week.  Plumbing, electrical and mechanical rough is about 80% complete. Final site grading and concrete curb and gutter are installed and the asphalt base for the private road will be installed on April 11 (from 180th to 174th St).  

    Comments (-1)
  • April 9, 2019

    Posted by Communications dept. on 4/9/2019

    Cafeteria/gym area is busy with interior wall framing, insulation and mechanical rough-in Sheetrock in the classrooms and office area is progressing well and casework is being installed. The cafeteria/gym area (pictured) is busy with interior wall framing, insulation and mechanical rough-in. Windows are being installed throughout the building; switchgear installed in the main electrical room. Water service to the building is complete and power is expected to be energized by early May.

    Comments (-1)
  • March 28, 2019

    Posted by Communications dept. on 3/28/2019

    Tambark Creek Elementary view from drone Tambark Creek Elementary School is progressing right along. Watch drone footage from inside the building. We're looking forward to seeing students and staff enter their new school this fall.

    Comments (-1)
  • March 12, 2019

    Posted by Communications on 3/12/2019

    Drone footage of Tambark Creek Elementary School Roofing is approximately 80% complete. Exterior siding and windows are being installed. Interior sheetrock is approximately 50% complete. Paint and tackable wall panels are being installed in the classroom wing. Plumbing, electrical and mechanical rough in continues. The new underground water and sewer systems are installed. The new underground storm sewer system is nearing completion. Final site grading and concrete curb and gutter are being installed at the new driveway that connects 180th street to 174th street. Wetland restoration work will complete by the end of the month. PUD has relocated four power poles along 174th street, which allows the contractor to install and complete the storm sewer in this area. Installation of the new underground electrical and low voltage conduits across 180th street will be complete by the end of the week.

    Comments (-1)
  • March 6, 2019

    Posted by Communications dept. on 3/6/2019

    Drone view of Tambark Creek Elementary

    At Tambark Creek Elementary, temporary heat has been installed in the building and the contractor continues to install interior wall framing, drywall, plumbing, electrical and mechanical rough in.

     

    Interior painting is underway and installation of roofing materials and exterior weather barrier is approximately 80 percent complete. Installation of windows and exterior cementitious siding is also underway.

     

    Though progress has been slowed by weather, the school is on schedule to open in September

    Comments (-1)