Tambark Creek ES project updates

  • October 9, 2019

    Posted by Communications on 10/9/2019

    School began on September 4 at Tambark Creek ES. The contractor is working on completing punch list items. Commissioning of the HVAC system, access control system and lighting control systems continue. Landscaping work is complete.

    Comments (-1)
  • September 9, 2019

    Posted by Communications on 9/9/2019

    School began on September 4 at Tambark Creek ES. The contractor is working on completing punch list items. Commissioning of the HVAC system, access control system and lighting control systems continue. Landscaping work is complete.

    Comments (-1)
  • August 15, 2019

    Posted by Communications on 8/15/2019

    The elevator, fire alarm system, fire sprinkler system and kitchen have been signed off by the associated inspector. All utilities are installed and operational. Paving of the parking lots is complete. Paving if the north access road that connects to 174th street will be complete before the start of school. Landscaping is underway. The under field drainage is complete at the play field and the contractor has begun placing topsoil on the play field. The play structure will be complete by the end of August. Classrooms are complete with the exception of punch list. The office staff has moved into the building with teachers to move in on August 19. Furniture has been delivered and distributed throughout the school.

    Comments (-1)
  • July 16, 2019

    Posted by Communications dept. on 7/16/2019

    Tambark Creek Elementary interior tour Check out the interior of Tambark Creek Elementary school! Crew is working hard to get it finished and ready to welcome new students on the first day of school.

    Comments (-1)
  • June 12, 2019

    Posted by Communications dept. on 6/12/2019

    The interior and exterior finishes are in process.  The contractor is installing the brown metal siding.  The concrete curbing and asphalt base for the road and parking areas are in process.  Utilities will be operational by mid-June.  Phone and fiber connections from the vendor are complete.   Elevator was delivered and is expected to be operational by 6/18.  90% of kitchen equipment and break-out store windows are installed.  The courtyard glass curtain wall is complete.

    Comments (-1)
  • June 4, 2019

    Posted by Communications dept. on 6/4/2019

    Drone photo of Tambark Creek as of June 2019

    Tambark Creek Elementary is on schedule for opening in fall of 2019. Interior and exterior finishes are in process and the contractor started installation of the brown metal siding in the courtyard. The concrete curbing and asphalt base for the road and parking areas are in process. Utilities will be operational by mid-June. The outline of the play toy area and the playground (with drainage) can be seen from this aerial photo.

    Comments (-1)
  • May 21, 2019

    Posted by Communications Dept. on 5/21/2019

    Casework being installed Installation of the large exterior store front windows began last week. Exterior windows and siding installation continues. The new boilers, pumps, and associated piping have been installed.

     

    The main electrical switch gear is nearing completion, with PUD scheduled to bring power to the building by the end of the month.

     

    Finish work is underway throughout the classroom wing, including casework, ceiling tile, wall coverings, white boards, painting, and interior glazing.

    Comments (-1)
  • May 7, 2019

    Posted by Communications dept. on 5/7/2019

    Tambark Creek Elementary School construciton site At Tambark Creek Elementary School exterior windows are being installed and roofing, interior sheetrock and lockers are complete.

     

    Tackable wall panels, white boards, and casework are being installed in the classroom wings. Floor polishing and ceramic tile will be complete this month. Plumbing, electrical and mechanical rough-in are about 95% complete. Parking-lot grading, exterior lighting, and curbing are in process.

    Comments (-1)
  • April 30, 2019

    Posted by Communications dept. on 4/30/2019

    Exterior windows are being installed. Roofing, interior sheetrock and lockers are complete. Tackable wall panels, white boards, casework are being installed in the classroom wings.  Floor polishing and ceramic tile will complete by mid-May.  Plumbing, electrical and mechanical rough are about 95% complete. Parking-lot grading, exterior lighting, and curbing are in process. Sidewalk sample will be reviewed 1st week of May before pouring.  Elevator install is planned for May 10.

    Comments (-1)
  • April 10, 2019

    Posted by Communications on 4/10/2019

    Roofing is approximately 98% complete. Exterior siding and windows are being installed. Interior sheetrock is approximately 75% complete. Paint and tackable wall panels are being installed in the classroom wings along with casework.  Floor polishing of the restrooms will be complete by 4/15 and tiling will complete the next week.  Plumbing, electrical and mechanical rough is about 80% complete. Final site grading and concrete curb and gutter are installed and the asphalt base for the private road will be installed on April 11 (from 180th to 174th St).  

    Comments (-1)