Woodside Elementary School project updates

  • Nov. 30, 2018

    Posted by Communications on 11/30/2018

    The Design Development drawings and specifications were released for review.  An open house is scheduled for December 11 from 5:00pm-7:00pm for the neighboring community to share the plans for Woodside ES’s modernization.  This communication process contributes to the State Environmental Policy Act (SEPA) submittal.

    Comments (-1)
  • Nov. 2, 2018

    Posted by Communications dept. on 11/2/2018

    Architects rendering of modernized school. Lots of windows, gated, secure entry.  The design development phase is complete and the more detailed construction design will continue for the next five to six months. Staff are securing the land-use permits. The request for construction bids will go out in spring 2019 with construction beginning next summer. The modernization will be in phases and there will be 10 portables on site, so students will be able to stay on campus during construction.

    Comments (-1)
  • Oct. 28, 2018

    Posted by Communications on 10/28/2018

    The design team is nearing the completion of the design development phase of design.

    Comments (-1)
  • Oct. 1, 2018

    Posted by Communications on 10/1/2018

    The architect presented the schematic design to the Woodside ES staff on September 26 with warm reception.  The architect and design team have started the design development as well as preparation for the permitting process with the county.

    Comments (-1)
  • Sept. 5, 2018

    Posted by Communications on 9/5/2018

    The schematic design is complete, and the architect is preparing a presentation that can be shown to staff by mid-September.  Next steps are starting the design development phase. The D-3 is scheduled to be submitted to OSPI in October.

    Comments (-1)
  • Aug. 15, 2018

    Posted by Communications on 8/15/2018

    The architect reviewed the latest schematic design (SD) costs with Facilities & Planning and they are within the budgeted construction costs.  This includes a couple of items to be considered as alternates for the bidding process.  The office design needs to be finalized and then the detailed design development will begin.

    Comments (-1)
  • Aug. 9, 2018

    Posted by Communications on 8/9/2018

    Studio Meng reviewed the VE recommendations and will provide updated plans for our review this week.

    Comments (-1)
  • Jul. 23, 2018

    Posted by Communications on 7/23/2018

    Studio Meng and Sazan Engineering presented at the July 16 value engineering (VE) & constructability review kickoff meeting.  The results meeting is scheduled for Wednesday, July 25.  A pre-application meeting with Snohomish County is schedule for July 25 regarding permitting.

    Comments (-1)
  • Jul. 12, 2018

    Posted by Communications on 7/12/2018

    Studio Meng is preparing the final schematic design (SD) package including drawings, and project binder with process and reports for presentation at the July 16 value engineering (VE) & constructability review kickoff meeting with Sazan Environmental Services.

    Comments (-1)
  • Jun. 29, 2018

    Posted by Communications on 6/29/2018

    Studio Meng is completing schematic design (SD) and the Facilities & Planning team will be reviewing the draft during the first week of July.

    Comments (-1)