Woodside ES project updates

  • February 3, 2020

    Posted by Communications on 2/3/2020

    Metal roof decking is in place on the new building, to be followed by roofing as weather allows.  The roof tie-ins for the A/B connector are underway.  The sub-floor in building A is going in this week.

    Comments (-1)
  • January 15, 2020

    Posted by Communications on 1/15/2020

    All floor slabs in the new building are in place and wall framing is just beginning as are rough-ins for mechanical and electrical.  In Building A, most of the sheetrock is up and taping is underway.  Painting is expected to take place at the end of the month, followed by pouring back the subfloor.  The A/B connector has walls framed with ceiling framing to begin next.

    Comments (-1)
  • January 2, 2020

    Posted by Communications on 1/2/2020

    Most of the structural steel for the new building is standing.  The erectors are working on finishing details.  The second floor slab in the new building is scheduled to be poured tomorrow, if weather cooperates.  The contractor is setting up temporary heat in Building A to enable work with finishes to continue.

    Comments (-1)
  • December 16, 2019

    Posted by Communications on 12/16/2019

    About half of the structural steel has been erected for the new building.  The floor slab connecting building A and B has been poured and framing has begun.  Drywall is underway in Building A. Preparations are wrapping up for receiving the mechanical units in both buildings.  Due to several unforeseen conditions, the schedule for occupying Building A has been moved to Spring break and occupancy of Building G (office/library) has been moved to Summer.  The overall scheduled end date for the project has not changed at this time.

    Comments (-1)
  • December 2, 2019

    Posted by Facilities & Planning on 12/2/2019

    Concrete work at the utility yard on the East side of building A is underway. The setting of structural steel for the new building begins this week. Underground rough-in is underway for the new connector between buildings A and B. Framing in building A is 95% complete. Mechanical and electrical rough-ins are nearly complete as well.

    Comments (-1)
  • November 19, 2019

    Posted by Facilities & Planning on 11/19/2019

    The final portion of the new office building footing has been poured today and the ground floor slab will be poured on 11/18/19.  Mechanical and electrical rough-in work continues in building A.  Shear walls are in progress and framing is 85% complete.

    Comments (-1)
  • October 15, 2019

    Posted by Communications on 10/15/2019

    Foundation walls and underground rough-in continues for the new building.  Shear wall foundations in building A will be poured later this week.  Mechanical and electrical rough-ins are underway in building A, along with framing.

    Comments (-1)
  • October 1, 2019

    Posted by Communications on 10/1/2019

    The foundation walls for the new building continue and underground rough-in has begun.  Work has started on the new shear wall foundations in building A.  Gravel is being placed to harden the site on the south side to enable construction access during the rainy season.

    Comments (-1)
  • September 16, 2019

    Posted by Communications on 9/16/2019

    School started on 9/4/19, as scheduled, with a slight modification to the parking lot to accommodate construction activities for the new building and fencing to separate the construction areas from the school zone.  The library has been divided enabling the addition of a class room there and two portables were added over the summer.  These new spaces, along with some other minor changes, and the reduction in enrollment due to boundary changes with the opening of Tambark Creek ES, allowed us to empty building A for this phase of the project.  Selective demolition for building A is nearly complete.  Footings for the new office/library building have been poured and foundation walls are being framed and readied for concrete.

    Comments (-1)
  • August 30, 2019

    Posted by Communications on 8/30/2019

    The school is nearly ready for students.  Final inspections on the two new portables are schedule for next Tuesday and some fencing to define the construction areas is being placed.  The A Building has been emptied and selective demolition is underway.  The sitework in the area of the new building has been completed and preparations for building foundations are underway.  The school will open with a slight alteration to the parking lot to reroute the traffic loop just a bit away from the construction of the new building.  Some other operational changes will be in place to accommodate the loss of the East courtyard due to construction.

    Comments (-1)