March 12, 2019

Posted by Communications on 3/12/2019

Drone footage of Tambark Creek Elementary School Roofing is approximately 80% complete. Exterior siding and windows are being installed. Interior sheetrock is approximately 50% complete. Paint and tackable wall panels are being installed in the classroom wing. Plumbing, electrical and mechanical rough in continues. The new underground water and sewer systems are installed. The new underground storm sewer system is nearing completion. Final site grading and concrete curb and gutter are being installed at the new driveway that connects 180th street to 174th street. Wetland restoration work will complete by the end of the month. PUD has relocated four power poles along 174th street, which allows the contractor to install and complete the storm sewer in this area. Installation of the new underground electrical and low voltage conduits across 180th street will be complete by the end of the week.