March 6, 2019

Posted by Communications dept. on 3/6/2019

Drone view of Tambark Creek Elementary

At Tambark Creek Elementary, temporary heat has been installed in the building and the contractor continues to install interior wall framing, drywall, plumbing, electrical and mechanical rough in.

 

Interior painting is underway and installation of roofing materials and exterior weather barrier is approximately 80 percent complete. Installation of windows and exterior cementitious siding is also underway.

 

Though progress has been slowed by weather, the school is on schedule to open in September