April 9, 2019

Posted by Communications dept. on 4/9/2019

Cafeteria/gym area is busy with interior wall framing, insulation and mechanical rough-in Sheetrock in the classrooms and office area is progressing well and casework is being installed. The cafeteria/gym area (pictured) is busy with interior wall framing, insulation and mechanical rough-in. Windows are being installed throughout the building; switchgear installed in the main electrical room. Water service to the building is complete and power is expected to be energized by early May.