April 10, 2019

Posted by Communications on 4/10/2019

Roofing is approximately 98% complete. Exterior siding and windows are being installed. Interior sheetrock is approximately 75% complete. Paint and tackable wall panels are being installed in the classroom wings along with casework.  Floor polishing of the restrooms will be complete by 4/15 and tiling will complete the next week.  Plumbing, electrical and mechanical rough is about 80% complete. Final site grading and concrete curb and gutter are installed and the asphalt base for the private road will be installed on April 11 (from 180th to 174th St).