April 30, 2019

Posted by Communications dept. on 4/30/2019

Exterior windows are being installed. Roofing, interior sheetrock and lockers are complete. Tackable wall panels, white boards, casework are being installed in the classroom wings.  Floor polishing and ceramic tile will complete by mid-May.  Plumbing, electrical and mechanical rough are about 95% complete. Parking-lot grading, exterior lighting, and curbing are in process. Sidewalk sample will be reviewed 1st week of May before pouring.  Elevator install is planned for May 10.