June 12, 2019

Posted by Communications dept. on 6/12/2019

The interior and exterior finishes are in process.  The contractor is installing the brown metal siding.  The concrete curbing and asphalt base for the road and parking areas are in process.  Utilities will be operational by mid-June.  Phone and fiber connections from the vendor are complete.   Elevator was delivered and is expected to be operational by 6/18.  90% of kitchen equipment and break-out store windows are installed.  The courtyard glass curtain wall is complete.