August 15, 2019

Posted by Communications on 8/15/2019

The elevator, fire alarm system, fire sprinkler system and kitchen have been signed off by the associated inspector. All utilities are installed and operational. Paving of the parking lots is complete. Paving if the north access road that connects to 174th street will be complete before the start of school. Landscaping is underway. The under field drainage is complete at the play field and the contractor has begun placing topsoil on the play field. The play structure will be complete by the end of August. Classrooms are complete with the exception of punch list. The office staff has moved into the building with teachers to move in on August 19. Furniture has been delivered and distributed throughout the school.