April 15, 2019

Posted by Communications on 4/15/2019

OSPI has signaled that the D-6 answer to the D-5 submittal is about to go out. Constructability Review comments have been reviewed and incorporated into the design as applicable. Construction documents at about 95% completion were received today and will be reviewed in preparation for going out to bid on 5/1/19. An option to relocate the school to the former Alderwood MS site has been reviewed and rejected, the modernization will continue as an occupied modernization project with four phases.