December 2, 2019

Posted by Facilities & Planning on 12/2/2019

Concrete work at the utility yard on the East side of building A is underway. The setting of structural steel for the new building begins this week. Underground rough-in is underway for the new connector between buildings A and B. Framing in building A is 95% complete. Mechanical and electrical rough-ins are nearly complete as well.