December 16, 2019

Posted by Communications on 12/16/2019

About half of the structural steel has been erected for the new building.  The floor slab connecting building A and B has been poured and framing has begun.  Drywall is underway in Building A. Preparations are wrapping up for receiving the mechanical units in both buildings.  Due to several unforeseen conditions, the schedule for occupying Building A has been moved to Spring break and occupancy of Building G (office/library) has been moved to Summer.  The overall scheduled end date for the project has not changed at this time.