January 15, 2020

Posted by Communications on 1/15/2020

All floor slabs in the new building are in place and wall framing is just beginning as are rough-ins for mechanical and electrical.  In Building A, most of the sheetrock is up and taping is underway.  Painting is expected to take place at the end of the month, followed by pouring back the subfloor.  The A/B connector has walls framed with ceiling framing to begin next.