April 1, 2020

Posted by Communications on 4/1/2020

Finishes are nearly complete in building A and furniture arrived today.  In building G, the boilers have been started, the fire alarm is online and HVAC is undergoing functional testing.  Windows are 60% installed. Work is underway to tie the existing low voltage systems to the new ones in order to re-establish campus wide connectivity for intercom, intranet, phones, security, etc.