April 15, 2020

Posted by Communications on 4/15/2020

The carpet has been installed in building A and the building is substantially complete.  In building G, sheetrock installation is taking place on the upper floor and finishing on the lower level.  The last of the windows are being installed this week.  Building B has been emptied of furniture and school contents and selective demolition is underway beginning its modernization process.  The cafeteria/gym building is being packed with movers scheduled at the end of this week to remove school contents and furniture, thereby allowing an early start since school is out until the fall.