June 15, 2020

Posted by Facilities and Planning on 6/30/2020

Framing in building B is nearly complete as is spray foam in the walls.  Evaluating sub-floor prior to placement of topping slab.  Carpentry crews are working on structural upgrades in building D.  In building G, ceiling grid is well underway and most casework is set.  Underground utilities continue along the bus loop, coordinated for allowing access to the school as needed.