May 15, 2020

Posted by Facilities and Planning on 5/29/2020

Inspections were passed today allowing teachers to work in building A.  They will setup their new classrooms next week.  Shear wall footings have been poured in building B, openings have been framed for the new windows and the glu-lam beam work is underway.  The gym/cafeteria, building D, has had abatement completed and the next round of demolition is nearly complete.  Building E, the existing office/library is packed preparing for the move into the new office/library building at the end of the summer.  Building G, the new office/library, is in the finishing stage with painting underway on the lower level and sheetrock sanding on the upper.  Storefront material is expected to be installed next week.  Excavation has begun beside the bus loop in order to place a rockery wall and wide the bus lane beside the gym.