North Middle School

The North Middle School modernization will remodel the main gymnasium areas, a new 2-story classroom building to accommodate 30 general education classrooms, and a new 1-story administration building, while retaining the recently constructed auxiliary gymnasium. Site work is expected to include new perimeter fencing and upgrades to the track and field.
 
  Location   2514 Rainier Ave., Everett, WA 98201
  Architect   NAC Architects
  Contractor   TBD
  Estimated project cost   $50,100,00
  Estimated completion
  August, 2019
 
Project update as of April 12, 2017
The Educational Specifications have been approved by the Board of Directors and the Schematic Design (SD) was well received by them. Design work is proceeding on schedule. The Value Analysis process began on 4/10/17 with report due on 4/21/17.
 
North MS Modernization Education Specifications Presentation - April 11, 2017, Board of Directors Meeting