North Middle School

  • Project information

  • North Middle School has a history of building related problems and a design that does not properly meet current program needs, introduces very little natural light, has circulation problems and needs updating for current security protocols. This project addresses those issues and more with a new 2-story classroom building abutting the existing gym complex to accommodate 30 general education classrooms, while retaining the recently constructed auxiliary gymnasium. The main gym and music areas have suitable structure and will be fully modernized. Site work will include a new main parking lot with improved drop-off lane, new perimeter fencing and upgrade of the track and field to synthetic surfaces.
     
     
      Location   2514 Rainier Ave., Everett, WA 98201
      Architect   NAC Architects
      Contractor   TBD
      Estimated project cost   $50,100,000
      Estimated completion   August, 2019
     
     
     Additional resources
     
    North MS Modernization Education Specifications Presentation - April 11, 2017, Board of Directors Meeting