  • The Woodside Elementary School renovation will modernize three classroom buildings and the gymnasium/cafeteria building; as well as construct a new two-story administration and library building. Site work includes additional fencing for safety improvements. Design work for the project is well underway. Construction began in the summer of 2019, with the completion of the project in the spring of 2021. 

     

      Location   17000 23rd Ave SE, Bothell, WA 98012
      Architect   Studio Meng Strazzara Architects
      Contractor   Edifice GC
      Estimated project cost   $27,800,000
      Estimated completion   Spring, 2021