Silver Firs ES Flooring Replacement
-
Estimated project cost $690,000
Estimated construction start date June 2023
Estimated/final completion date August 2023
-
Description
The project includes removal of the existing floor coverings in the classrooms, hallways, and cafeteria; and installation of new floor coverings in the above listed spaces.
Updates
August, 2023: Project is complete
July 1, 2023: The contractor is well underway with demolition of the old flooring and installation of new carpet and rubber flooring in the classrooms and corridor in C building.April 11, 2023: The district is under contract and anticipating the commencement of the work at the end of the school year.
February 13, 2023: District staff is finalizing the flooring selections and bid drawings for the project which will take place summer 2023.December 21, 2022: The first meeting with school staff has taken place and design concepts have been presented. Another design meeting will take place in January for material selections.
December 6, 2022: District staff are currently working on material selections with the design team and the school staff.
October 25, 2022: Design will begin in November.