Silver Firs ES Flooring Replacement

  • Estimated project cost                           $690,000
    Estimated construction start date        June 2023
    Estimated/final completion date          August 2023

  • Description

    The project includes removal of the existing floor coverings in the classrooms, hallways, and cafeteria; and installation of new floor coverings in the above listed spaces.

    Updates

    August, 2023:  Project is complete

    July 1, 2023: The contractor is well underway with demolition of the old flooring and installation of new carpet and rubber flooring in the classrooms and corridor in C building.

    April 11, 2023: The district is under contract and anticipating the commencement of the work at the end of the school year.   

    February 13, 2023: District staff is finalizing the flooring selections and bid drawings for the project which will take place summer 2023.

    December 21, 2022: The first meeting with school staff has taken place and design concepts have been presented. Another design meeting will take place in January for material selections.

    December 6, 2022: District staff are currently working on material selections with the design team and the school staff.

    October 25, 2022: Design will begin in November.