- Reader Board Replacements
Capital Projects
Page Navigation
Reader Board Replacements
-
Estimated project cost $400,000 per phase
Estimated construction start date Varies
Estimated final completion date Ongoing
-
Description
New electronic reader boards are being installed district wide, in phases over the next two or three years. Phase one installations, which are complete, include Cascade HS, Hawthorne ES, Silver Lake ES and Silver Firs ES. Phase two reader boards include Emerson ES, Garfield ES, Jefferson ES, Penny Creek ES, and North MS. Phase three reader boards include Jackson HS, Gateway MS, Sequoia HS and Evergreen MS. Design of subsequent phases will begin in 2024.
Updates
February 11, 2025: The district is working on reader boards for Sequoia HS, Mill Creek ES and Whittier ES. The reader board design for Mill Creek ES has been approved and currently in for permit approval. We are working on the electrical design and drawings. Sequoia is still in permit process. We are starting the design for Whittier’s reader board this month.
December 1, 2024: District is working on reader boards for Sequoia HS, Mill Creek ES and Whittier ES.
August 19, 2024: No updates.
May 1, 2024: Sequoia HS and Mill Creek ES are in for permits.February 7, 2024: Reader boards for Sequoia HS, Mill Creek ES and Everett HS are in design. Evergreen MS will be installed on February 8, 2024.
November 1, 2023: Recent installations have been completed at Jackson HS and Gateway MS.
July 1, 2023: The reader board at Jackson HS is scheduled for installation in late July. The reader board at Gateway MS is scheduled for installation at the end of August.
April 11, 2023: Reader Boards have been installed at Jefferson ES, Emerson ES, Garfield ES and North MS. Penny Creek ES installation is pending. Design for Sequoia HS, Gateway MS and Evergreen MS is under way.
February 13, 2023: Phase One reader boards are complete at Cascade HS, Hawthorne ES, Silver Lake ES and Silver Firs ES. Phase Two reader boards are underway, with electrical installation complete at Penny Creek ES, Emerson ES, and Jefferson ES. Electrical installation is scheduled for Garfield ES the week of February 20. Surveying of the property line at North Middle School is underway to ensure proper placement of the new reader board. Phase Two reader boards will be installed this spring and summer, depending on the delivery schedule. Phase Three will include new reader boards at Sequoia HS, Gateway MS, and Evergreen MS and Jackson HS, and is in the planning stage.
December 21, 2022: Phase One reader boards are completed at Cascade, Hawthorne, Silver Lake and Silver Firs. Phase Two reader boards at Penny Creek ES, Emerson ES, Garfield ES, Jefferson ES and North MS are expected to be installed in winter/spring of 2023. Conduits were installed under the parking lot of Penny Creek during winter break. Phase Three reader boards will be installed at Sequoia HS, Gateway MS, Evergreen MS and Jackson HS by the end of 2023.