Jackson HS Telescoping Seating (complete)
-
Estimated project cost $370,000
Estimated start date Summer 2024
Estimated/final completion date Summer 2024Description
This project will include replacement of the telescoping seating in the commons.
Updates
August 18, 2024: The new telescoping seating has been installed and is operational.
May 1, 2024: The bleachers and gym floor have been removed. The flooring contractor has materials on site and will begin to install plywood next week.April 1, 2024: No new updates.
November 9, 2023: We are under contract with KCDA and Nor-Pac Seating in anticipation the project will commence at the end of the school year.