Everett HS Lincoln Field synthetic turf replacement (completed)

This project includes replacement of the existing synthetic turf surface with new synthetic turf surface. The old surface is worn out due to age and a high rate of use, and is in need of replacement. The original field was installed in 2004.

  Location   1898 25th St, Everett, WA 98201
  Architect   DA Hogan
  Contractor   Coast to Coast Turf
  Estimated project cost   $1,500,000
  Estimated completion   Fall 2018 - COMPLETED
 
Ariel view of finished field Project update as of September 28, 2018 
The new synthetic turf surface is finished, new backstop netting installed and students are enjoying the field!
 
 
 
 
 
 
Project update as of September 12, 2018 
The contractor achieved substantial completion on August 8, 2018. The last pending item is owner training.
 
Project update as of August 9, 2018 
The contractor has completed the installation of the new synthetic turf surface. Site clean-up is underway. New backstop netting is being installed.
 
Old turf removed and ready for new turf to be installed Project update as of July 9, 2018 
The contractor has removed and disposed of the old synthetic turf. They have made needed modifications to the existing under-field drainage system and leveled the crushed rock base layer. Currently the contractor is paving the rubberized e-layer. The e-lay is a padding that is installed under the synthetic turf field.
 
 
 
 
 
Project update as of June 14, 2018 
Coast to Coast is under contract. They received the Notice to Proceed on June 7, 2018 and are scheduled to begin work on site on June 18, 2018. We have accepted COP-001 to upgrade the turf to a heavier fabric.
 
Project update as of May 10, 2018 
Coast to Coast Turf is the low bidder for the project. The school board accepted their bid on May 8, 2018. The contract paperwork is being prepared to send out.
 
Lincoln field prior to new turf being installed, old and worn Project update as of April 11, 2018 
The project went out to bid on April 4, the second advertisement date was April 10). The walk through of the project site is April 12. The bids are due on April 24.
 
 
 
 
 
 
Project update as of March 2, 2018 
The drawings and project specifications are being finalized to go out for bid.
 
Project update as of February 2, 2018 
DA Hogan is continuing to move forward with design. The team is gathering feedback from coaches regarding the existing deign. The team will incorporate this information into the new design.
 
Project update as of February 9, 2017
Design of this project is scheduled to begin fall, 2017.