Capital Projects
Page Navigation
Gateway MS Distributed Antenna System (completed)
This project is required by the Snohomish County Fire Marshall and will include a new distributed antenna system (DAS) installation.
Location | Gateway MS | ||
Estimated project cost |
$150,000
|
||
Estimated completion | Winter 2020-21 | ||
Funding source | TBD |
September, 2021
This project is complete.
June 8,2021
The project work is in process. The fire alarm panel at Gateway will be replaced to accommodate the new points for the DAS system. The work will take place during the summer.
April 27, 2021
The project work is in process.
April 13, 2021
The project work is in process.
March 11, 2021
The project work began in January 2021 and is currently underway.
November 25, 2020
The project has been awarded to Structured Communications and work will start onsite in December.
November 12, 2020
We have held a pre-bid meeting for contractors to view the site and conditions.
October 8, 2020
Hargis is working on design of the system with Dykeman working on the architectural part for the two hour rated room.
September 9, 2020
Harigs has been requested to submit a fee proposal for the design, bid documents and construction administration work for installing a DAS at Gateway MS. This project is required by code.