Return to Headlines

Bleacher handrail upgrades (completed)

Project includes replacement of worn, missing or substandard bleacher handrails at Jackson HS, Gateway MS, and Heatherwood MS.  
 
 
  Location   JHS, GMS, HMS
  Estimated project cost   $85,000
  Estimated completion   2020-21
  Funding source   General Fund 

 

March 2021
The work is complete at this time.  District staff will do an inspection of the work with the contractor. 

February 2021
The work at Heatherwood is complete. Work at Jackson HS and Gateway MS will follow after February 22, 2021.    

January 20, 2021
Work is in process at Heatherwood MS to add safety materials to the bleachers.  Work at Jackson HS and Gateway MS will follow.   

December 9, 2020
District staff are working with the vendor to determine added safety materials to the bleachers at the three schools. 

November 25, 2020
We are working with the vendor to determine added safety materials to the bleachers at the three schools. 

November 10, 2020
The bleacher vendor is currently working on a second revised estimate to include some additional safety components. 

October 27, 2020
The bleacher vendor is currently providing an updated quote for the project.