Cedar Wood ES Distributed Antenna System (completed)
This project is required by the Snohomish County Fire Marshall and will include a new DAS system installation.
Location | Cedar Wood ES | ||
Estimated project cost |
$150,000
|
||
Estimated completion | Spring/Summer 2021 |
December 6, 2021
The project is complete and the first responder radio system is functional at Cedar Wood Elementary.
September 15, 2021
The onsite work is underway.
June 8, 2021
The project has been awarded to Structured Communications. The work will commence after June 21,2021.
April 27, 2021
The project is out to bid. Bids are due on Friday, May 7, 2021.
April 13, 2021
Project design work is in process.
March 11, 2021
The district has begun the project design.
February 11, 2021
The district will begin our project design.