- Everett Public Schools
- Other Capital Projects
Capital Projects
Page Navigation
Everett Memorial Stadium Synthetic Turf and Track Replacement (completed)
The scope of work includes the removal of the existing synthetic turf and track surfaces and the installation of a new football/soccer synthetic turf field and synthetic track surface.
Location | Everett Memorial Stadium | ||
Estimated project cost | $1,325,000 | ||
Estimated completion | Summer 2022 | ||
Funding Source | 2016 Levy |
September 29, 2022
The project is substantially complete. We are working on close out items.
August 17, 2022
The project is substantially complete and available for use.
July 8, 2022
June 8, 2022
Astro Turf (Coast to Coast) has completed the removal of the old turf. FieldTurf (Beynon) has completed most of the track removal.
May 18, 2022
The contract with FieldTurf (Beynon) has been signed and executed. A Notice to Proceed (NTP), dated May 23, 2022, has been issued. FieldTurf’s first day is scheduled for May 31. Coast to Coast is scheduled to begin work on-site on Monday, May 23.
April 13, 2022
Turf contractor – AstroTurf (Coast to Coast) has signed and returned their original contract. We have issued a PO to KCDA. The Notice to Proceed (NTP), dated May 23, 2022, has been sent to Coast to Coast. Track contractor – FieldTurf (Beynon) has signed the contract.
March 7, 2022
Working with KCDA to get contracts fully executed. The turf submittals have been approved.
February 8, 2022
KCDA is processing the contracts with the contractors.
January 13, 2022
We've received pricing for both the synthetic turf field and synthetic track surface. AstroTurf Corporation will do the synthetic turf scope of the project. The submitted price is $608,355. Beynon Sports Surfaces will do the synthetic track scope of the project work. The submitted price is $402,457. Documents have been submitted to KCDA for review and pricing verification.
December 1, 2021
The design work and project manual are complete. Pricing from the vendor is due on December 15.
October 13, 2021
The design team is continuing to work on the design elements for the field and track.
September 1, 2021
The design team is meeting to determine the design elements of the field and track.
July 1, 2021
Architect selection is complete.