Return to Headlines

Gateway MS Chiller Replacement (completed)

Replacement of the Gateway MS chiller.

  Location   Gateway MS
  Estimated project cost   $250,000
  Estimated completion   Spring 2022
  Funding source   School Construction Assistance Program (SCAP)

September 29, 2022
Punch list, training and close out remains. 

September 1, 2022
The new chiller started as scheduled on August 24 and was placed in service on August 25. 

August 2, 2022
The old chiller has been removed.  The new chiller is scheduled to ship on August 3, 2022.  There is an updated schedule in place with the goal of getting the new unit on-line prior to the start of school, provided there are no more delays.

May 2, 2022
The expected delivery date is the end of May.

April 1, 2022
The contractor is working on obtaining the chiller delivery date.

March 1, 2022
MacDonald Miller is under contract. The chiller submittal has been reviewed and returned to the contractor; ordering is underway.

January 4, 2022 
The bid-set is in for review.

October 4, 2021 
Hargis has visited the site and begun the design work.

April 28, 2021 
Sazan has been hired to begin the engineering and is working on the scope of work and ballpark estimate.